Data transferred using Microsoft Project/Microsoft Project Server

This topic provides details on the data transferred between DOVICO Timesheet and Microsoft Project/Project Server when specific actions are performed using the Microsoft Project or Microsoft Project Server Link.

This topic assumes the reader has working knowledge of Microsoft Project and DOVICO Timesheet's Microsoft Project/Project Server Link.

 

Add/Get Resources

Clicking the Add/Get Resources button transfers all employees from the Microsoft Project/Project Server Resource pool to the DOVICO Timesheet database. If Get Resources is selected a second time, only new and modified employees are synchronized back to DOVICO Timesheet. After its initial use, the Add/Get Resources button only needs to be used when modifications or additions are made to the Microsoft Project/Project Server resource pool.

The employee first and last names and email addresses are transferred from Microsoft Project to DOVICO Timesheet. Employee properties are editable in DOVICO Timesheet except for the employee's First and Last name.

 Microsoft Project/Project Server

 

 DOVICO Timesheet

Resource first name

Employee first name

Resource last name

Employee last name

Resource email address (optional)

Employee email address

 

 

Add Projects

Clicking the Add Project button transfers the selected project, its tasks and resource assignment details from Microsoft Project/Project Server to DOVICO Timesheet. The Add Project button is only required when a new project is sent from Microsoft Project/Project Server to DOVICO Timesheet.

Microsoft Project/Project Server

 

DOVICO Timesheet

Projects

Projects

Tasks

Tasks

Resource Assignments

Task Assignments

Work

Estimate hours

Assignment Start and Finish dates

Assignment Start and Finish dates

WBS code (optional)

WBS code

 

 

Get Assignments

Clicking the Get Assignments button updates the task assignments information from Microsoft Project/Project Server to DOVICO Timesheet. That is; resources assigned to the tasks, new tasks (if any), task scheduled Start and Finish dates, estimated hours and WBS codes. This function should be used after modifications are made to the Microsoft Project/Project Server plan file.

Microsoft Project/Project Server

 

DOVICO Timesheet

Tasks

Tasks

Resource Assignments

Task Assignments

Work

Estimate hours

Assignment Start and Finish dates

Assignment Start and Finish dates

WBS code (optional)

WBS code

 

 

Send Time

Clicking the Send Time button sends approved time from DOVICO Timesheet to Microsoft Project/Project Server.

DOVICO Timesheet

 

Microsoft Project/Project Server

Approved time

Actual Work

ETCs (optional)

Remaining Work

Status date (optional)

Project Status date

 

 

Synchronize All