Use DOVICO Timesheet's Microsoft Project Server Link to link project and task assignments created in Microsoft Project Server to DOVICO Timesheet. When a link is created, employees use DOVICO Timesheet to track time on the task assignments created in Microsoft Project Server. When time entries are submitted and approved, the actual hours worked are updated in Microsoft Project Server files.
Click here to see an overview of the information being transferred using the Microsoft Project Server Link.
This topic describes the fundamental steps
required to setup and
synchronize data from Microsoft Project Server to DOVICO Timesheet.
Details on how to send time entries from DOVICO Timesheet to Microsoft
Project Server are described in Send
time to Microsoft Project Server.
STEP 1: Establish the connection to Microsoft Project Server.
STEP 2: Synchronize the Resource pool.
STEP 3: Synchronize projects, employees and task assignments from the Microsoft Project Server file.
Prerequisite:
The Microsoft Project Server link requires ActiveX controls and therefore only browsers capable of supporting ActiveX controls can be used to link Microsoft Project Server files to DOVICO Timesheet. The Mozilla Firefox browser does not support ActiveX (verified January 2008). Limited functionality is available without ActiveX controls, see Notes below.
|
Notes:
|
STEP 1: Establish connection information
Select Microsoft
Project
from the Integration section of the side navigation bar.
Select the Project Server Link tab.
In the Connection Information area, enter the Microsoft Project Server URL.
Select your login Authentication format.
Enter the Microsoft Project Server Authentication User ID and Password.
If using Windows Authentication and entering a domain user account, then the User account must be formatted as 'userid@domainname'. For version 9.1 of DOVICO Timesheet, the following format can also be used: 'domainename\userid'
Click the Apply
button.
|
Warning: Before moving to the next step you must ensure that you have added a Microsoft Project Server Account in Microsoft Project under Tools, Enterprise Options, Microsoft Office Project Server Accounts. After which you will be prompted to connect to a Microsoft Project Server Account each time you access Microsoft Project. |
STEP 2: Synchronize the Resource pool
When a Microsoft Project Server resource pool is linked to DOVICO Timesheet, employees assigned to each project are automatically added to the DOVICO Timesheet database.
|
Warnings:
|
Start Microsoft Project Server.
From DOVICO Timesheet, select the Project Server Link tab.
Click the Get Resources button located below the Resource list box.
|
Microsoft Project Server |
|
DOVICO Timesheet |
|
Resource first name |
|
Employee first name |
|
Resource last name |
|
Employee last name |
|
Resource email address (optional) |
|
Employee email address |
For each employee added, you will need to edit their User ID and Password information as random data is entered in these fields when an employee is added from the resource pool. You will also need to modify the Software access field for each new employee as 'None' is selected by default. Use either the Project Assignment view's employee list or the Items List - Employees view to edit this information.
|
Note: If a synchronized employee in the Microsoft Project Server resource pool file is ever deleted, that employee will remain in the DOVICO Timesheet database. |
STEP 3: Create a link in DOVICO Timesheet
When a link is created:
The project is added to the list of projects in DOVICO Timesheet. You can edit project information in DOVICO Timesheet without affecting the link or Microsoft Project Server files.
Tasks are not added to the list of tasks in DOVICO Timesheet. However, the tasks are displayed in the Project Assignments view and are available to employees entering time.
Prerequisite:
DOVICO Timesheet only supports task assignments
from the bottom level tasks in the Microsoft Project Server file. Also,
do not leave any blank rows in the Microsoft Project Server file's Gantt
chart view. Additional details
![]()
|
DOVICO Timesheet only supports the lowest level task assignments in Microsoft Project Server. Assignments made to group level tasks are not supported. Assignments made at the lowest task levels are supported.
Assignments made at the group level are not supported.
DOVICO Timesheet does not support blank rows in a Microsoft Project Server file. Any blank rows within a Microsoft Project Server file must be removed prior to creating the link.
|
Click the Add Project button located below the Project list box.
A pop-up window opens listing all Microsoft Project Server projects not currently linked to DOVICO Timesheet.
Select a project from the list and click OK.
The project, its tasks and assignments are added to DOVICO Timesheet. The project (with the "published" extension) and its tasks are displayed in the Project Assignments view. You cannot add or edit assignments using the Project Assignments view.
|
Microsoft Project Server |
|
DOVICO Timesheet |
|
Projects |
|
Projects |
|
Tasks |
|
Tasks |
|
Resource Assignments |
|
Task Assignments |
|
Work |
|
Estimate hours |
|
Assignment Start and Finish dates |
|
Assignment Start and Finish dates |
|
WBS code (optional) |
|
WBS code |
The project assignments are now created in DOVICO Timesheet and employees can begin tracking their time against this project.
Click here to see how to send time from DOVICO Timesheet to the Microsoft Project Server file.
|
Notes:
|