Send time to Microsoft Project Server

This topic describes how to send approved time from DOVICO Timesheet to Microsoft Project Server.

To send time to Microsoft Project Server files:

  1. Login to Microsoft Project Server.

  2. From DOVICO Timesheet, select Microsoft Project from the Integration section of the side navigation bar.

  3. Select one or more projects from the Project list box.

    When DOVICO Timesheet sends time to Microsoft Project, it sends the time as total hours (or additional hours). No information regarding the dates when time was actually worked is sent to Microsoft Project. Microsoft Project places the hours received from DOVICO Timesheet in its scheduled period or around the project status date (see step 5 below).

    Simplified example: In DOVICO Timesheet, for a given task, 2 hours are entered on Monday, 3 hours on Tuesday and 4 hours on Friday. When this time is sent from DOVICO Timesheet to Microsoft Project, a total of 9 hours are sent and Microsoft places these 9 hours in its scheduled period. If the scheduled period was Monday through Friday, 8 hours will be placed on Monday and 1 hour will appear on Tuesday.
     

  4. Click the Send Time button located below the Resource list box.

  5. A pop-up window opens showing the previous status date and how many hours are ready to be submitted for each project selected in step 3.  

    If the selected project has an established previous status date, you should continue to use the Status Date option, otherwise you may experience unexpected results within Microsoft Project.

    Two options are available when sending time to Microsoft Project Server:

Status date option:

Send ETC option:

  1. Click OK.

 

Approved time is sent to the Microsoft Project file.

DOVICO Timesheet

 

Microsoft Project Server

Approved time

Actual Work

ETCs (optional)

Remaining Work

Status date (optional)

Project Status date

 

Notes:

  • Only approved time in DOVICO Timesheet is sent to Microsoft Project.

  • The list of projects displayed in the Project list box may be limited if Limited Access to projects is applied to the user.

  • In Microsoft Project, if no ETCs are received from DOVICO Timesheet, the Remaining Work is equal to Work minus Actual Duration.

  • If a time entry is deleted from DOVICO Timesheet, the corresponding time will not be removed from Microsoft Project Server.

  • If using the Project Status date option, you may find that some uncompleted tasks are not automatically moved past the Status date. You can control whether or not uncompleted work is rescheduled. Search for "Reschedule uncompleted work" in Microsoft Project Server's help file.

 

Tip: Press the Synchronize All button to automatically Get Resources, Get Assignments and Send Time for the selected projects.