ETC
The ETC
column (Estimate to Complete) displayed at the far right of the timesheet
grid is an optional column used by employees to enter how many hours
they estimate are required to
complete the task.
ETC values are sent to the database and enable
managers to view estimated time to completion reports to aid in tracking
project development and employee efficiency.
|
Notes:
The
ETC column can be hidden. See Options.
Historical
ETC values are not saved. The ETC value entered for a task in a given
week appears in all previous and future weeks.
ETCs
are not submitted along with time entries but are immediately updated
in the database whenever an ETC value is added or modified.
When
an ETC value of 0 is entered for a task, it is displayed as "Complete"
in various administrative views and reports.
The
ETC value is also displayed in the Time Entry Details area (Task
Progress Information).
|